EDIT MAIN
Plus_blue

View the Live Stream of the 
Eisenhower Middle School now.

Bond Highlights

SIP 2017 Bond Thank You videos

Below is our new, more informative bond report format. You made the impossible happen, so we are committed to ensuring that everyone knows as much as possible about our bond progress. 


Progress Corner 

septEMBER 2019:

EISENHOWER MIDDLE SCHOOL MAJOR 2017 FACILITY BOND PROJECTS 

-44% Complete
-Brick veneer is being installed on the east & south sides
-Installation of CMU in kitchen area
-Tiling started in restrooms
-Joist & columns in progress for commons area
-Furniture 95% design review

SAFE ROOMS (*PHASE 1) 

-Almor West: Substantial Completion
-Carriage Hills: Substantial Completion
-Crosby Park: Substantial Completion
-Edison: Substantial Completion
-Hugh Bish: Substantial Completion
-Sullivan Village: Substantial Completion
-Woodland Hills: Substantial Completion
-Whittier: In-Progress

ATHLETIC TRACK RESURFACING:

-MacArthur High School: PROJECT COMPLETE
-Eisenhower High School: In-Progress
-Lawton High School: In-Progress

WINDOW PROJECTS:

-Eisenhower High School: PROJECT COMPLETE
-Lawton High School: Awaiting completion of punch list items
-MacArthur High School: PROJECT COMPLETE

HVAC PROJECTS:

-Adams Elementary, Almor West Elementary, Lincoln Elementary, MacArthur Middle, Tomlinson Middle and Woodland Hills: PROJECTS COMPLETE

ROOF PROJECTS:

-Lawton High School, Tomlinson Middle School, John Adams Elementary, Carriage Hills Elementary, Edison:
PROJECTS COMPLETE

MHS CAFETERIA PROJECTS:

-Awaiting O&M manuals and completion of punch list items
-Fire Alarm Upgrade: In-Progress

MHS HVAC AUDITORIUM, GYM & ADMIN PROJECT:

-Contract approved by Board in August
-95% Review 9/19/19
-Advertise bids 10/03/19

EQUIPMENT, TECHNOLOGY & FURNITURE:

-Classroom furniture ordered with summer delivery
-2700 Chromebooks deployed to 6 secondary sites (EHS, LHS, MHS, MMS, CMS, EMS)
-Tomlinson Middle School is already a 1:1 site with iPads, and that was made possible through a Federal Grant
-Replacement of the projector and Smartboard setups with 4K 65” Interactive Flat Panel (a touchscreen TV) for 129 classrooms throughout the district
-Band Instruments purchased
-Band Uniforms purchased for EHS, LHS, & MHS
-Flooring, carpeting, gym wall pads, ceiling fans, lighting, mini-blinds and air conditioning upgrades & purchases
-Instructional software licenses, books & materials purchased district-wide
-Textbooks purchased & Textbook Software purchased
-Transportation GPS system & cameras
-Library books & supplies

ELEMENTARY GYM REPAIRS:

-Almor West: Substantial Completion
-Carriage Hills & Crosby Park: Permits approved by City. Construction awaiting PO

FENCING:

-Fencing studies started


District staff members have worked extremely hard to move as fast as possible. We owe it to you to deliver on this bond and to keep you informed.  (*View SIP Project Updates)